Question / Soalan 1 (15 marks / markah)

Company FTZ is planning to move its office to a bigger and more strategic location to serve its customers better. This is because the company is growing exponentially and the current working space is insufficient. The need of a larger, more modern facility to accomplish business goals for the future is pressing. The moving contract was signed one month ago and is expected to be implemented in the next few weeks.

You have been hired as the project manager, and you are expected to prepare the following key deliverables of the project plan.

a) Construct Network Diagram. Perform CPM analysis and the calculation of LS, EF, ES, LF, and TF based on Table 1 below. Identify the activities on the critical path. (7.5 marks)

b) Construct an S-curve and calculate SV, CV, SPI, and CPI. Comment on the status of the project (Refer to Table 2 and Table 3 below). (7.5 marks)

[Let’s say today is July 1st (Day 45) and the following data is available:
Total EV(BCWP)=60,000, AC(ACWP)=65,000, PV(BCWS)=60,000,
BAC (Budget Cost at Completion) =200,000]

Assume that the ‘Moving Project’ has 10 activities as shown in Table 1.

Syarikat FTZ merancang untuk memindahkan pejabatnya ke lokasi yang lebih besar dan strategik untuk memberi perkhidmatan yang lebih baik kepada pelanggannya. Ini adalah kerana syarikat itu sedang berkembang pesat dan ruang kerja semasa tidak mencukupi. Keperluan kemudahan yang lebih besar dan lebih moden untuk mencapai matlamat perniagaan masa depan adalah mendesak. Kontrak pemindahan itu telah ditandatangani sebulan lalu dan dijangka akan dilaksanakan dalam beberapa minggu akan datang.

Anda telah diupah sebagai pengurus projek, dan anda dijangka menyediakan hasil utama perancangan projek berikut.

a) Bina Gambarajah Rangkaian. Lakukan analisis CPM dan pengiraan LS, EF, ES, LF, dan TF berdasarkan Jadual 1 di bawah. Kenal pasti aktiviti-aktiviti di laluan kritikal. (7.5 markah)

b) Bina satu lengkungan S dan kira SV, CV, SPI, dan CPI. Beri komen tentang status projek (Rujuk Jadual 2 dan Jadual 3 di bawah). (7.5 markah)

[Katakan hari ini ialah 1 Julai (Hari 45) dan data berikut tersedia:
Jumlah EV(BCWP)=60,000, AC(ACWP)=65,000, PV(BCWS)=60,000,
BAC (Kos Belanjawan Semasa Siap) =200,000]

Andaikan ‘Projek Bergerak’ mempunyai 10 aktiviti seperti yang ditunjukkan dalam Jadual 1.

Stuck in This Assignment? Deadlines Are Near?

Table 1 / Jadual 1

ID Activity/Aktiviti IPA Duration/Tempoh(days/hari)
A Plan move/Menggerak perancangan 20
B Kickoff meeting/Mesyuarat kickoff A 1
C Select furniture/Pemilihan Perabot B 25
D Prepare office/ Penyediaan pejabat B 20
E Set up utilities/Pemasangan Utiliti A 30
F Install new signs/ Pemasangan papan tanda baru B 15
G Complete internal construction/Penyiapan pembinaan dalaman A 45
H Install new furniture/computers/Pemasangan perabot/komputer baru C,G 10
I Move/relocate/Menggerak/Ubah lokasi D, H,E 5
J Close out project/Penutupan projek F,I 5

Table 2 / Jadual 2

ID Activity/Aktiviti BCWS Planned Finish/Penyiapan Perancangan
A Plan move/Menggerak perancangan $5,000 May 10/Mei 10
B Kickoff meeting/Mesyuarat kickoff $2,000 May 14/Mei 14
C Select furniture/Pemilihan Perabot $3000 June 15/ Jun 15
D Prepare office/ Penyediaan pejabat $20,000 June 24/ Jun 24
E Set up utilities/Pemasangan Utiliti $30,000 July 1/Julai 1
F Install new signs/ Memasang papan tanda baru $3,500 July15/Julai 15
G Complete internal construction/Penyiapan pembinaan dalaman $5000 July 5/Julai 5
H Install new furniture/computers/Pemasangan perabot/komputer baru $80,000 July 20/Julai 20
I Move/relocate/Menggerak/Ubah lokasi $50,000 July 28/Julai 28
J Close out project/Penutupan projek $1500 Aug 1/Ogos 1
Total/Jumlah 200,000

Table 3 / Jadual 3

Activity/Aktiviti BCWS Planned Finish/ Penyiapan Perancangan Current Status/Status Terkini Actual Cost/Kos Sebenar (AC) Earned Value/Nilai Diperolehi (EV)
Plan move/Menggerak perancangan $5,000 May 10/Mei 10 Completed/Siap $5,000 $5,000
Kickoff meeting/Mesyuarat kickoff $2,000 May 14/Mei 14 Completed/Siap $1,800 $2,000
Select furniture/Pemilihan Perabot $3000 June 15/Jun 15 Completed/Siap $3,000 $3,000
Prepare office/ Penyediaan pejabat $20,000 June 24/Jun 24 60% Completed/Siap $11,000 $12,000
Set up utilities/Pemasangan Utiliti $30,000 July 1/Julai 1 Completed/Siap $36,700 $30,000
Install new signs/ Memasang papan tanda baru $3,500 July15/ Julai 15 Completed/Siap $3,500 $3,500
Complete internal construction/Penyiapan pembinaan dalaman $5000 July 5/ Julai 15 90% complete/Siap $4,000 $4,500
Install new furniture/computers/Pemasangan perabot/komputer baru $80,000 July 20/Julai 20 0 0 0
Move/relocate/Menggerak/Ubah lokasi $50,000 July 28/Julai 28 0 0 0
Close out project/Penutupan projek $1500 Aug 1/Ogos 1 0 0 0
200,000 $60,000

Get 30% Discount on This Assignment Answer Today!

Question / Soalan 2 (15 marks / markah)

A municipal council is considering two alternative proposals to accommodate an increasing assembly. Two schemes exist:

1) Extension of the existing building with modifications to the old building (7.5 marks)

2) Demolition and rebuilding (7.5 marks)

Sebuah majlis perbandaran sedang mempertimbangkan dua cadangan alternatif untuk menampung perhimpunan yang semakin meningkat. Terdapat dua skim seperti berikut:

1) Pembesaran bangunan sedia ada dengan pengubahsuaian kepada bangunan lama (7.5 markah)

2) Perobohan dan pembinaan semula (7.5 markah)

The following are the financial implications:

Berikut adalah implikasi kewangan:

Scheme 1 / Skim 1

Proposed extension, including fees 120,000.00
Repairs and modifications 80,000.00
Major repairs every 15 years 15,000.00
General maintenance per annum 2,000.00
Redecoration every eight years 10,000.00
Heating per annum 1,800.00
Lighting and cleaning per annum 1,000.00
Insurance per annum 900.00

Scheme 2 / Skim 2

Demolition, sale of materials etc. -30,000.00
Building and fees 350,000.00
General maintenance per annum 500.00
Redecoration every 10 years 9,000.00
Heating per annum 900.00
Lighting and cleaning per annum 800.00
Insurance per annum 750.00

Evaluate the above proposals and suggest other factors that may need to be considered where both project building life are 60 years, and the discount rate is 20%.

Nilaikan cadangan di atas dan cadangkan faktor-faktor lain yang mungkin perlu dipertimbangkan di mana kedua-dua hayat pembinaan projek adalah 60 tahun dan kadar diskaun ialah 20%.

Question / Soalan 3 (10 marks / markah)

An organization is about creating a control and communication system that allows management to achieve its objectives. It puts in place a structure that defines roles, hierarchies, communication, coordination, and control mechanisms.

a) Define the term organizational design and identify the crucial variables that should be considered in the design of such an organization. With appropriate sketches, compare between functional organization structure and divisional organization structure. (5 marks)

b) After a project is completed and in use by the owner, a formal meeting should be held with representative from the owner’s organization to obtain feedback regarding the performance of the project. Explain the importance of obtaining the feedback. (5 marks)

Get Solved Your Assignment( variable) and Earn A+ Grade!

Sebuah organisasi sedang mewujudkan sistem kawalan dan komunikasi yang membolehkan pengurusannya mencapai objektif. Ia mempunyai struktur yang mentakrifkan peranan, hierarki, komunikasi, penyelarasan dan mekanisme kawalan.

a) Takrifkan istilah reka bentuk organisasi dan kenal pasti pembolehubah penting yang perlu dipertimbangkan dalam reka bentuk organisasi tersebut. Dengan lakaran yang sesuai, bandingkan antara struktur organisasi berfungsi dan struktur organisasi bahagian. (5 markah)

b) Selepas projek disiapkan dan digunakan oleh pemilik, satu mesyuarat rasmi hendaklah diadakan dengan wakil daripada organisasi pemilik untuk mendapatkan maklum balas mengenai prestasi projek. Terangkan kepentingan mendapatkan maklum balas. (5 markah)

 

Get Help By Expert

Are you stressed about your Project Management Assignment? There's no need to worry! We are here to assist and provide zero-AI Assignment Help Malaysia of high quality with original content written by our PhD expert writers. We will make sure your assignment will be completed on time by our management assignment helpers. Also, we have free assignment samples for students so that you can get an idea of ​​the quality. Now, stop worrying about late submissions and contact us for the best grades!

Answer

UP TO 15 % DISCOUNT

Instant Paper Writing Services by Native Malaysia Writers

Plagiarism Free Solutions
100% Original Work
24*7 Online Assistance
Native PhD Experts
Hire a Writer Now
Convincing Features
Plagiarism Free Report
On-Time Delivery
Native Writers
A+ Quality
100% Confidential
24*7 Online Assistance

Get these features included in Your Assignment

Get Assistance for Assignments, online Exam, and Projects Writing