Company FTZ is planning to move its office to a bigger and more strategic location to serve its customers better. This is because the company is growing exponentially and the current working space is insufficient. The need of a larger, more modern facility to accomplish business goals for the future is pressing. The moving contract was signed one month ago and is expected to be implemented in the next few weeks.
You have been hired as the project manager, and you are expected to prepare the following key deliverables of the project plan.
a) Construct Network Diagram. Perform CPM analysis and the calculation of LS, EF, ES, LF, and TF based on Table 1 below. Identify the activities on the critical path. (7.5 marks)
b) Construct an S-curve and calculate SV, CV, SPI, and CPI. Comment on the status of the project (Refer to Table 2 and Table 3 below). (7.5 marks)
[Let’s say today is July 1st (Day 45) and the following data is available:
Total EV(BCWP)=60,000, AC(ACWP)=65,000, PV(BCWS)=60,000,
BAC (Budget Cost at Completion) =200,000]
Assume that the ‘Moving Project’ has 10 activities as shown in Table 1.
Syarikat FTZ merancang untuk memindahkan pejabatnya ke lokasi yang lebih besar dan strategik untuk memberi perkhidmatan yang lebih baik kepada pelanggannya. Ini adalah kerana syarikat itu sedang berkembang pesat dan ruang kerja semasa tidak mencukupi. Keperluan kemudahan yang lebih besar dan lebih moden untuk mencapai matlamat perniagaan masa depan adalah mendesak. Kontrak pemindahan itu telah ditandatangani sebulan lalu dan dijangka akan dilaksanakan dalam beberapa minggu akan datang.
Anda telah diupah sebagai pengurus projek, dan anda dijangka menyediakan hasil utama perancangan projek berikut.
a) Bina Gambarajah Rangkaian. Lakukan analisis CPM dan pengiraan LS, EF, ES, LF, dan TF berdasarkan Jadual 1 di bawah. Kenal pasti aktiviti-aktiviti di laluan kritikal. (7.5 markah)
b) Bina satu lengkungan S dan kira SV, CV, SPI, dan CPI. Beri komen tentang status projek (Rujuk Jadual 2 dan Jadual 3 di bawah). (7.5 markah)
[Katakan hari ini ialah 1 Julai (Hari 45) dan data berikut tersedia:
Jumlah EV(BCWP)=60,000, AC(ACWP)=65,000, PV(BCWS)=60,000,
BAC (Kos Belanjawan Semasa Siap) =200,000]
Andaikan ‘Projek Bergerak’ mempunyai 10 aktiviti seperti yang ditunjukkan dalam Jadual 1.
ID | Activity/Aktiviti | IPA | Duration/Tempoh(days/hari) |
---|---|---|---|
A | Plan move/Menggerak perancangan | – | 20 |
B | Kickoff meeting/Mesyuarat kickoff | A | 1 |
C | Select furniture/Pemilihan Perabot | B | 25 |
D | Prepare office/ Penyediaan pejabat | B | 20 |
E | Set up utilities/Pemasangan Utiliti | A | 30 |
F | Install new signs/ Pemasangan papan tanda baru | B | 15 |
G | Complete internal construction/Penyiapan pembinaan dalaman | A | 45 |
H | Install new furniture/computers/Pemasangan perabot/komputer baru | C,G | 10 |
I | Move/relocate/Menggerak/Ubah lokasi | D, H,E | 5 |
J | Close out project/Penutupan projek | F,I | 5 |
ID | Activity/Aktiviti | BCWS | Planned Finish/Penyiapan Perancangan |
---|---|---|---|
A | Plan move/Menggerak perancangan | $5,000 | May 10/Mei 10 |
B | Kickoff meeting/Mesyuarat kickoff | $2,000 | May 14/Mei 14 |
C | Select furniture/Pemilihan Perabot | $3000 | June 15/ Jun 15 |
D | Prepare office/ Penyediaan pejabat | $20,000 | June 24/ Jun 24 |
E | Set up utilities/Pemasangan Utiliti | $30,000 | July 1/Julai 1 |
F | Install new signs/ Memasang papan tanda baru | $3,500 | July15/Julai 15 |
G | Complete internal construction/Penyiapan pembinaan dalaman | $5000 | July 5/Julai 5 |
H | Install new furniture/computers/Pemasangan perabot/komputer baru | $80,000 | July 20/Julai 20 |
I | Move/relocate/Menggerak/Ubah lokasi | $50,000 | July 28/Julai 28 |
J | Close out project/Penutupan projek | $1500 | Aug 1/Ogos 1 |
Total/Jumlah | 200,000 |
Activity/Aktiviti | BCWS | Planned Finish/ Penyiapan Perancangan | Current Status/Status Terkini | Actual Cost/Kos Sebenar (AC) | Earned Value/Nilai Diperolehi (EV) |
---|---|---|---|---|---|
Plan move/Menggerak perancangan | $5,000 | May 10/Mei 10 | Completed/Siap | $5,000 | $5,000 |
Kickoff meeting/Mesyuarat kickoff | $2,000 | May 14/Mei 14 | Completed/Siap | $1,800 | $2,000 |
Select furniture/Pemilihan Perabot | $3000 | June 15/Jun 15 | Completed/Siap | $3,000 | $3,000 |
Prepare office/ Penyediaan pejabat | $20,000 | June 24/Jun 24 | 60% Completed/Siap | $11,000 | $12,000 |
Set up utilities/Pemasangan Utiliti | $30,000 | July 1/Julai 1 | Completed/Siap | $36,700 | $30,000 |
Install new signs/ Memasang papan tanda baru | $3,500 | July15/ Julai 15 | Completed/Siap | $3,500 | $3,500 |
Complete internal construction/Penyiapan pembinaan dalaman | $5000 | July 5/ Julai 15 | 90% complete/Siap | $4,000 | $4,500 |
Install new furniture/computers/Pemasangan perabot/komputer baru | $80,000 | July 20/Julai 20 | 0 | 0 | 0 |
Move/relocate/Menggerak/Ubah lokasi | $50,000 | July 28/Julai 28 | 0 | 0 | 0 |
Close out project/Penutupan projek | $1500 | Aug 1/Ogos 1 | 0 | 0 | 0 |
200,000 | $60,000 |
A municipal council is considering two alternative proposals to accommodate an increasing assembly. Two schemes exist:
1) Extension of the existing building with modifications to the old building (7.5 marks)
2) Demolition and rebuilding (7.5 marks)
Sebuah majlis perbandaran sedang mempertimbangkan dua cadangan alternatif untuk menampung perhimpunan yang semakin meningkat. Terdapat dua skim seperti berikut:
1) Pembesaran bangunan sedia ada dengan pengubahsuaian kepada bangunan lama (7.5 markah)
2) Perobohan dan pembinaan semula (7.5 markah)
The following are the financial implications:
Berikut adalah implikasi kewangan:
Proposed extension, including fees | 120,000.00 |
Repairs and modifications | 80,000.00 |
Major repairs every 15 years | 15,000.00 |
General maintenance per annum | 2,000.00 |
Redecoration every eight years | 10,000.00 |
Heating per annum | 1,800.00 |
Lighting and cleaning per annum | 1,000.00 |
Insurance per annum | 900.00 |
Demolition, sale of materials etc. | -30,000.00 |
Building and fees | 350,000.00 |
General maintenance per annum | 500.00 |
Redecoration every 10 years | 9,000.00 |
Heating per annum | 900.00 |
Lighting and cleaning per annum | 800.00 |
Insurance per annum | 750.00 |
Evaluate the above proposals and suggest other factors that may need to be considered where both project building life are 60 years, and the discount rate is 20%.
Nilaikan cadangan di atas dan cadangkan faktor-faktor lain yang mungkin perlu dipertimbangkan di mana kedua-dua hayat pembinaan projek adalah 60 tahun dan kadar diskaun ialah 20%.
An organization is about creating a control and communication system that allows management to achieve its objectives. It puts in place a structure that defines roles, hierarchies, communication, coordination, and control mechanisms.
a) Define the term organizational design and identify the crucial variables that should be considered in the design of such an organization. With appropriate sketches, compare between functional organization structure and divisional organization structure. (5 marks)
b) After a project is completed and in use by the owner, a formal meeting should be held with representative from the owner’s organization to obtain feedback regarding the performance of the project. Explain the importance of obtaining the feedback. (5 marks)
Sebuah organisasi sedang mewujudkan sistem kawalan dan komunikasi yang membolehkan pengurusannya mencapai objektif. Ia mempunyai struktur yang mentakrifkan peranan, hierarki, komunikasi, penyelarasan dan mekanisme kawalan.
a) Takrifkan istilah reka bentuk organisasi dan kenal pasti pembolehubah penting yang perlu dipertimbangkan dalam reka bentuk organisasi tersebut. Dengan lakaran yang sesuai, bandingkan antara struktur organisasi berfungsi dan struktur organisasi bahagian. (5 markah)
b) Selepas projek disiapkan dan digunakan oleh pemilik, satu mesyuarat rasmi hendaklah diadakan dengan wakil daripada organisasi pemilik untuk mendapatkan maklum balas mengenai prestasi projek. Terangkan kepentingan mendapatkan maklum balas. (5 markah)